Muzahmiyya Pipelines & Water Tank

Overview

Our team delivered the Muzahmiyya Pipelines & Water Tank project as a full turnkey infrastructure scope. The work covered all civil and structural works, including excavation, trenching, pipe bedding, thrust blocks, chambers, and valve rooms, along with the supply and installation of water transmission pipelines, fittings, valves, and associated appurtenances. The scope also included the construction of the water storage tank, including foundations, reinforced concrete works, waterproofing, and all mechanical and electrical connections, followed by hydrostatic testing, disinfection, flushing, commissioning, and handover. The project was executed under strict safety, quality, and schedule controls, with close coordination with the client and consultants throughout all phases, and the facilities were handed over fully operational on schedule.